400kV Transmission Line at Barguna, Bangladesh.

Taltoli, Barguna

The transmission line will consist of high-voltage towers that will be installed along the route from the Taltoli power plant to the national grid. The towers will support high-voltage power lines that will carry the electrical power generated by the power plant to the national grid. The transmission line will be designed to minimize power losses during transmission, which will ensure that the electrical power generated by the power plant reaches its destination with minimal energy loss.

This is 400kV high-voltage power transmission line from the 307MW (NET) coal-fired power generation facility.

Line Lenght: 27 km

SERVICES

  • Design & Consultancy
  • Supervision

Head Office: 1/1-A, Adabor Bazar Road, Dhaka-1207, Bangladesh